Roadmap standard

How to build, present and keep a roadmap true.

A roadmap shows your epics in order over time. It is true only if the dates are true.

What it contains

For every epic: a title, an owner, a start date, a due date, a status and its dependencies.

How to build it

  1. List your epics.
  2. Order them by value, risk and dependency.
  3. Write one sentence for why each comes where it does.
  4. Add start and due dates.
  5. Mark dependencies (“B cannot start before A ends”).
  6. Write what you chose not to do.

Forms of a roadmap

Form Where Notes
Timeline view in your git host Paid tiers of some hosts Draws bars from epic dates
Table in a file Any free account Works everywhere. See the epic roadmap template.
Milestone list Any free account Each milestone has a date and shows progress

Use what your account supports. The discipline is the same.

Present it in five minutes

  1. The goal of the product in one sentence.
  2. The epics in build order.
  3. One risk.
  4. One date that changed and why.
  5. What you chose not to do.

Leaders want the picture, not the issues.

Three views, kept true

  • Roadmap for leaders: when will each part land?
  • Board for the weekly meeting: what is blocked?
  • Issue list for builders: what is the next ready task?

If the views disagree, the builder builds the wrong thing.

Rules

  • Change a date the same day the truth changes.
  • An epic with no dates is not on the roadmap.
  • An epic untouched for two months is a lie on the roadmap. Update or close it.
  • A true red bar is useful. A false green bar is harmful.